Cat A Fit Out with Refurbishment

77-79 Farringdon Road background image
  • Works were conducted on levels 1 to 6
  • Each floor consisting of approximately 3,800sqft of office space and central core WC facilities
  • Removal of an existing concrete staircore to increase lettable floor area
  • Mechanical & electrical works upgrades
  • Refurbishment or renewal of the raised access flooring
  • Repairs and redecoration throughout
  • Upgrade of lighting installations (LED)
  • Alterations or upgrade of power distribution within the raised access floor
  • Reception area upgrade and refurbishment
  • Main communal area upgrade and refurbishment including reconfiguration of toilet areas
  • Removal of the concrete escape staircase and central lift shaft to the rear of the premises
  • Forming an opening in the wall of the spiral staircase to insert sections of glazed partition on each landing
  • Alteration of partitions forming the communal landing, WC’s and stores
  • External refurbishment
  • Work to alter basement bike store and shower and toilet install

  • Peter Russell

    Construction Manager

  • Colin Lewis

    Commercial Manager